Local City Bicycling Initiatives
Big Island
CONNECTING COMMUNITIES, CONSERVATION AND AMENITIES
Big Island Soil & Water Preservation Association, NFP, Inc.
2005 to 2020 Four Phase Plan Big Island Map 2005-2015
Phase 1: "Lock 31 Big Island Day Use Area"
Trail connection plans
2011-2015
Part 1: Big Island Centennial 20 by 24 foot Litchfield Steel hip roof Picnic Shelter, concrete pad, and two commercial grade picnic tables and other commercial grade picnic accessories completed and dedicated to the Illinois Department of Natural Resources November 2007 in celebration of 100 years of the Hennepin Canal.
Part 2: Multi-use trail connection at Lock 31 including two ADA bike /walk access ramps, bike parking, sidewalks and soft barrier landscaping.
Part 3: New 10 foot wide bridge and sanitary facilities.
Part 2: Multi-use trail connection at Lock 31 including two ADA bike /walk access ramps, bike parking, sidewalks and soft barrier landscaping.
Part 3: New 10 foot wide bridge and sanitary facilities.
Phase 2: Mirror Lake Gardens
2011-2020
Part 1: Landmark Herron Statue 10Õ to 15Õ tall with granite rock base in Mirror Lake
Part 2: Eco Friendly 1.1 mile bike path around lake and connecting to Big Island/Milan levee bike path and Milan neighborhood and business streets
Part 3: Ground Preparation and installation of Garden Areas
Part 4: Observation Deck, Seating, and Trail & Nature Information Centers
Part 2: Eco Friendly 1.1 mile bike path around lake and connecting to Big Island/Milan levee bike path and Milan neighborhood and business streets
Part 3: Ground Preparation and installation of Garden Areas
Part 4: Observation Deck, Seating, and Trail & Nature Information Centers
Phase 3: Neighborhood Bike/walk path connections for Big Island and Milan connecting the amenities and businesses of both.
Part 1: Outline "Complete Streets Program" plans for Big Island and Milan
Part 2: Obtain approvals for plans and funding
Part 3: Construct one successful project after another within plan
Part 2: Obtain approvals for plans and funding
Part 3: Construct one successful project after another within plan
2011-2020
Phase 4: Complete bike path from Lock 30 to Lock 32
Part 1: Resurface levee bike path from Highway 67 Bridge to West Pump Station at Lock 31
Part 2: Resurface levee bike path from Lock 30 to Mill Creek
Part 3: Extend Levee Bike path from Lock 31 to Lock 32
Part 4: Connect to Great River Trails System
Part 2: Resurface levee bike path from Lock 30 to Mill Creek
Part 3: Extend Levee Bike path from Lock 31 to Lock 32
Part 4: Connect to Great River Trails System